Know-how

Drilling methods

A profound understanding of the manufacturing and drilling processes is required in order to develop optimised machinery and tools for special foundation industry. At KLEMM Bohrtechnik, this expertise flows directly into the products.

Grouted anchors

Production and drilling methods

The tie-back of excavations by means of strand anchors is a frequently encountered application in special foundation engineering. This application and manufacturing process is characterised by characteristic production phases. 

The borehole for the installation of the strand anchor can be produced with different drilling methods. When selecting the most suitable drilling method, the existing subsoil in particular is a very important factor. The entirety of all specific technical components required for the respective drilling method represent the drilling system.

Production sequence

Phase 1

Drilling of the borehole by using a drilling method adapted to the boundary conditions (type of ground, groundwater, adjacent buildings ...).

Production sequence

Phase 2

Extraction (pulling) of the drill rods after or during the filling and grouting with cement and installation of the anchoring tendon.

Production sequence

Phase 3

Subsequent grouting of the anchor. Increased suspension pressure causes the grout body to burst open. The resulting cracks or fissures are post-grouted, if necessary several times with cement supension.

Production sequence

Phase 4 (a)

Acceptance testing and fixing of the anchors. The steel tendon is tensioned by a hollow piston jack beginning with a high pressure test load. In stepped load cycles, it is tensioned and released down to the design load several times. At each stage the time-dependent settling behaviour ("creeping") of the grout body in the subsoil and the elastic behaviour of the free tendon length are recorded.

Production sequence

Phase 4 (b)

If the creep of the component reaches a steady state and the required free tendon length is satisfactory then the tendon is finally fastened and wedged in place using the anchor head plate. A test protocol is prepared for every anchor. Protruding strand ends are removed and the anchor head is covered by a cap. This completes the manufacturing process of the anchor.

Production of ground achors on a construction site

 

Clear demonstration of all phases of securing an excavation pit wall using temporary strand anchors. Very informative video of BAUER Spezialtiefbau GmbH.

Pleaseaccept marketing-cookiesto watch this video.

Drilling methods

There are various methods of producing a drilled hole. At the time of the invention of the grouted anchor it was mainly ramming a pipe with lost drill bit, thus dispacing the soil. For non-cohesive soils pipes with an external diameter of 76 mm were very widely used. The rotary drilling method with staged drill bits or roller bits was used in cohesive soils. Higher anchor forces and additional post grouting pipes mounted on the tension member soon made greater drilling diameters necessary. The expansion of the traffic routes called for even more stabilisation of slopes with extremely long permanent anchors - and this too placed more demands on the drilling depths. These could range from 40 to 60 m, and in exceptional cases even 100 m. This exceeded the depths achievable at the time with ramming of about 20 m, and with a compressed air driven rotary percussion to around 30 m. Pure flushing bore methods - as generally used in water well drilling - couldn’t tackle this due to the associated fine soil washout and risk of subsidence.

Back then a new process and drilling tools were developed by KLEMM Bohrtechnik, for example for overburden drilling with a hydraulic drifter. The term overburden drilling comes from the fact that the outer casing and drilling rods first move together through all material (loose soil including rock) that overlays the bedrock horizon. As soon as solid rock is met, the outer casing is left in place and drilling is continued with just the drilling rods. Today the expression overburden drilling is used for almost all drilling where loose soil with rock is found near the surface.

The limits of classic overburden drilling are determined by the presence of intercalating loose and firm rock formations because the casing advanced by rotation only cannot get through rock shelves and in addition loose rock layers below the shelf normally collapse.

This problem was resolved using the double-head drilling procedure. The outer casing contains its own casing crown and the drill rods rotated in opposite directions and were driven forward by a hydraulic drifter. This was a crucial step forward, particularly for intercalation drilling. In addition, this drilling system made it possible to drill through sheet-pile walls, diaphragm walls and bored pile walls even at high external water overpressure and, in this way, reliably prevent water and soil deprivation and hence hazardous settlement in the excavation pit environment during the entire production process for the anchor.

Recently, new ways have been developed in special foundation indudstry where, for some dedicated geologies, the impact movement of the chosen overburden drilling method is replaced by a vibrating movement. The noise level can be considerably reduced and the downward speed is further increased by overcoming skin friction, especially during the retraction of the drill rods. The rotary movement during retraction can also be dispensed with, thus avoiding torsion of the steel tendon.

Rotary drilling

with a single rod

Rotary drilling

with auger rods

Rotary percussion drilling

with a hydraulic drifter and a single rod and lost bit

Overburden drilling

with hydraulic drifter and double rod

Overburden drilling

rotary / rotary with double head drilling equipment and down-the-hole hammer

Overburden drilling

rotary / rotary percussion with double-head drilling equipment

Applications

Micropiles

Increase the load-bearing capacity of the foundation soil.

Applications

Anchor

Anchoring of a construction pit wall (pile wall, diaphragm wall, sheet pile wall, shored construction pit,...) .

Applications

Compensation grouting

Horizontal consolidation of the foundation soil to compensate for settlements that occur as a result of tunnel excavation. Applied where vertical access is not possible in densely built-up areas.

Applications

Rock grouting

Sealing or backfilling of fissured or karstic, usually rocky subsoil, e.g. in the construction of dams and underground structures.

Applications

Pore injection

Production of deep-lying, gap-free sealing bases in sand and gravel.

Applications

Compaction injection

Improving the bearing capacity of a mostly loose subsoil by compacting it without breaking it up.

Temporary anchors

Temporary anchors, fully or partially removable, are used to secure construction projects, e.g. retaining walls for a lifetime of a maximum of two years. 

Permanent anchors

Permanent anchors are grouted anchors with a service life from two years and beyond and are therefore part of the construction structure. The sheathing tubes of the strands and each cavity of the anchor head are filled with permanently plastic corrosion protection compound.